Commissioning
|
PegasusTSI – System Driven Commissioning
All PegasusTSI projects have a common commissioning
procedure:
- Systems are defined.
- System boundaries are determined.
- Critical project/plant interfaces are determined.
- Logical system turnover plan is part of the Master Schedule.
Common commissioning procedures include:
- Early turnover of infrastructure items by AREA turnover to including the roads, storm drains, water supply, steam, wastewater, air, security, communications and power to facilities
- Switch to Commissioning by SYSTEMS at the 80% milestone
- Construction identification of initial punch list
- Punch list priorities established
- Integrity checks and tests
- Flush and clean
- Complete restoration of systems
- Commissioning plant startup proceeds
- Mechanical completion certification
- Final functional loop checks
- "Mock" Commissioning implemented
- System Start-Up
- Finalize all punch list items
- Plant signoff
- Issue final turnover certificate
|
|
|
|
 |